Building-Process bpbanner1

Building Process House & Land

Building a new home is a uniquely special experience. At Everyday Homes, we take pride in accompanying you on this exciting journey, from selecting the ideal design to handing over the keys to your dream home. We believe in partnering with our customers throughout the entire building process, with our dedicated team providing support at every step. Our ultimate goal is to make your home building journey as enjoyable and stress-free as possible.

slash

Securing Your Home and Land Package – Select Package

placeholder coffee-table

✔️ Customer to pay a non-refundable reservation fee of $500. This will reserve the package for 14 days. 

✔️ In the meantime, Building Contract is prepared for signing. 

✔️ The Land Contract will be sent directly to customer’s solicitor. All this will occur within 7 days.

Customer Requirements
  • Customer’s solicitors’ details required in order for Land Contract to be issued.

Note:

* Customers have sought financial advice and are aware of their borrowing capacity.

* Preparation of Land Contract and Building Contracts run concurrently.

* There are additional fees for customers solicitors.

placeholder coffee-table

Building Contract

placeholder lounge

✔️ Build Contract is issued via DocuSign to customer.

✔️ Customer signs Building Contract.

✔️ Builder orders home owner warranty insurance.

✔️ Customer receives a $15,000.00 invoice for deposit payment. This payment will be deducted from the contract amount.

 

CUSTOMER REQUIREMENTS
  • The above noted documents must be accepted within the designated timeframe to maintain fixed site pricing.
placeholder lounge

Building and Land Contract Signing

placeholder two-ladies

✔️ Customer signs Building Contract via docusign

✔️ Customer signs Land Contract and pays 10% deposit of the contract price with their solicitor

Customer Requirements
  • The above noted documents must be signed & $15,000.00 payment is required within the designated timeframe to maintain fixed site pricing


Note:

* Contract Tender Contract Quotation and Building Contract terms and conditions cannot be varied

* Exchange of land contracts required within 14 days of issue 

placeholder two-ladies

Land Registration

placeholder two-builders

✔️ Customer to pay balance of land purchase price.


Customer Requirements
  • Land settlement to take place within 14 days of land registration with the LRSNSW unless otherwise noted. Balance of land purchase price to be paid.
placeholder two-builders

Finalisation and Approval

placeholder two-ladies-meeting

✔️ Estate Design Review Panel Approved (if applicable)

✔️ Everyday Home’s to lodge plans for building approval

✔️ Sydney Water Approved

✔️ DA/CDC Approved

✔️CC (Construction Certificate) Approved

Customer Requirements
  • Signed mortgage documents or owners’ capacity to pay.

  • Proof of ownership of land.

  • Customer to pay balance of 5% deposit prior to site start.


Note:

* Basix approval is subject to house type and orientation.

* Approval times will vary depending on the estate, developer, and the relevant council.

placeholder two-ladies-meeting

Meet Your Construction Co-ordinator

placeholder soft-chair

✔️ Internal Colour selections

✔️ Electrical design

✔️ Tile selection


Customer Requirements
  • Colour selections appointment to be finalised at our design studio hub at our main office during business hours.
placeholder soft-chair

Construction Commences

Slab Stage

✔️ Customer to pay progress payment of 15% 

✔️ Slab, external drainage and site works complete

Customer Requirements
  • Progress payment to be forwarded to lending institution by customer.

Note:

* You will meet your site supervisor

Frames Erected

✔️ Customer to pay progress payment of 20% 

✔️ Frames erected and windows installed

✔️ Frame stage complete

Customer Requirements
  • Progress payment to be forwarded to lending institution by customer.


Note:

* Site supervisor can be contacted to arrange a site meeting (if required).

Brickwork and Roof

✔️ Customer to pay progress payment of 20% 

✔️ Brickwork completed, and first floor roof tiles laid. 

✔️ Bricks may be cleaned, and first floor roof tiles bedded in the next stage. 

✔️ Kitchen has been made and stored ready for installation

Customer Requirements
  • Progress payment to be forwarded to lending institution by customer

Note:

* Site supervisor can be contacted to arrange a site meeting (if required).

Internals

✔️ Customer to pay progress payment of 15% 

✔️ Electrical rough in & internal linings substantially completed

Customer Requirements
  • Progress payment to be forwarded to lending institution by customer

Note:

* Site supervisor can be contacted to arrange a site meeting (if required).

Kitchen Installation

✔️ Customer to pay progress payment of 15% 

✔️ Kitchen installed, fix out substantially completed.

✔️ Wet area tiling substantially completed

✔️ Painting substantially completed

Customer Requirements
  • Progress payment to be forwarded to lending institution by customer.

Final Touch-ups and Balance

✔️ Customer to pay final and remaining balance of 10% 

✔️ Any final touches on the home are completed and finish practical completion items

✔️ Any agreed works from the inspection will be carried out as agreed with the owner.

Customer Requirements
  • Progress payment to be forwarded to lending institution by customer

Note:

* Site supervisor will contact you to arrange practical completion inspection

Handover

✔️ Keys are given, and you can move into your new home

Customer Requirements
  • Customer will come into the office to meet the construction co-ordinator for handover

Note:

* Defects liability period begins straight after handover and continues for 90 days.

placeholder two-builders

Defects liability and Warranty Care

placeholder corebuild

✔️ A one-time inspection day to address any issues will be scheduled on agreed date with customer


Customer Requirements
  • Customer to submit a one-time list of any defective items form within 90 days after settlement.


Note:

* Rectification works are completed Monday to Friday between 7am – 3.30pm unless agreed between trade

placeholder corebuild